TIDEL Park - Hyundai
Client; Architect;
TIDEL PARK Ltd. C.R.Narayana Rao & Associates / Tata Consulting Engineers.
o ACMV system.
Carried out the site activities of ACMV system works, which has 3000T of chiller with another 3000T of Thermal Energy storage system, which is world's third largest.
o Fire fighting system.
Executed the fire fighting system work consisting of Hydrant system, Sprinkler system catering to 1.28 million sq.ft. of office space and Mulsifyre system protecting 6 Transformers with a capacity of 10.5 MVA.
Was coordinator for Electrical, Fire Alarm, BMS and Elevator systems.
TIDEL PARK Ltd. C.R.Narayana Rao & Associates / Tata Consulting Engineers.
o ACMV system.
Carried out the site activities of ACMV system works, which has 3000T of chiller with another 3000T of Thermal Energy storage system, which is world's third largest.
o Fire fighting system.
Executed the fire fighting system work consisting of Hydrant system, Sprinkler system catering to 1.28 million sq.ft. of office space and Mulsifyre system protecting 6 Transformers with a capacity of 10.5 MVA.
Was coordinator for Electrical, Fire Alarm, BMS and Elevator systems.
Software Parks - Consolidated construction
http://www.ccclindia.com/
Worked as an Ast. General Manager handling three software technology parks apart from other jobs. Worked with respective project Managers reporting to me. CC was the main contractor in these projects.
M& E Project Management.
Client; Architect; MEP Value
o Ascendas –Taramani,Chennai Team 3 51.01 crores.
o Hexaware – Chennai Team 3 16.19 crores.
o Ascendas – MIPL, Chennai CRN 59.28 crores.
Worked as an Ast. General Manager handling three software technology parks apart from other jobs. Worked with respective project Managers reporting to me. CC was the main contractor in these projects.
M& E Project Management.
Client; Architect; MEP Value
o Ascendas –Taramani,Chennai Team 3 51.01 crores.
o Hexaware – Chennai Team 3 16.19 crores.
o Ascendas – MIPL, Chennai CRN 59.28 crores.